Quantcast
Channel: Midwest IT Survival » product roadmap
Viewing all articles
Browse latest Browse all 10

Single View of the Work, Part 10

$
0
0

Consider tracking team member vacations on your resource plan

Consider tracking team member vacations on your resource plan

As a manager of a team of IT engineers, one of the toughest challenges is getting a handle on not only what everyone is working on, but what are all the seemingly unpredictable requests for work coming at your team. Thus whether you find yourself managing a new team or have been managing a team for some time but you are constantly being surprised with new requests out of left field, you may want to consider constructing a logical approach similar to what is being outlined in this series of articles to stop the surprises.

In the first article in this series, we identified the work request attributes of your team and built a list of sources of those requests. In the previous article, we finalized our Gantt chart listing all the work requests and projects by work phase and indicated which team member is work on which phase with durations and dependencies from your team’s estimation sheets. Additionally, your team review of the chart increased its accuracy and improved your team’s level of engagement again. This article will offer considerations on what additional, non-external work to reflect on the chart for improved reporting.

HR-ish Stuff

The first non-external work data items to consider adding to the team resource plan are company holidays, mandatory “all hands” meetings and team member vacations. Basically, consider adding all the HR-ish stuff that requires your team’s time that results in the loss of the ability to work on other “real” activities. You may want to establish a threshold for the duration of HR-ish stuff to add. You may recall we calculated a real work day of five or six hours assuming 1:1’s, fire drills, performance reviews and other interruptions previously. Thus, you may want to consider a minimum threshold of a full business day. A single hour one on one still allows a team member to complete a task on that same day. Contrarily, a full day off-site “all hands” meeting does not permit any “real” work to get accomplished on the day the meeting is scheduled. Thus, creating a break in the work all team members are performing on that specific “all hands” meeting day reflects the real world impact of such events on your team’s estimates and work delivery. Once added, all work delivery end dates should be pushed out a full day. In my experience, when estimating work, technical people rarely think through the impact of such business event. They don’t always realize the need to incorporate these events into their work delivery communications and expectations setting.

Vacations

Adding team member vacations is extremely helpful from multiple perspectives. For one, it is a great single place for you to keep that information. Your company may already have an HR administrative system that automates the process of keeping track of this information thus this benefit might be marginalized. But if you aren’t fortunate to have such a system, it can become a real hassle maintaining and updating a spreadsheet to track this information yourself. By incorporating this administrivia into your Gantt chart, keeping track becomes just another step in the process of keeping the chart data updated through team one on one discussions, etc. For our planning effort, the lager benefit for tracking such information is in the improved accuracy of establishing work request delivery end dates. If another 40 hours is needed for a team member to complete a specific work request but that team member is going to be out on vacation for the next five days, clearly that work request isn’t going to get completed for at least two weeks. By adding that team member’s five day vacation as a break in their work on that request, the new work delivery date now is more realistic. With this vacation break clearly noted in your chart, external parties have a clearer picture on what is making the request take, in this case, at least two weeks minimum instead of expecting the request to be completed next Friday.

In summary, consider a threshold of a day for HR-ish work events and the following activities to be worthy of explicit Gantt chart reporting as material breaks to in-flight work:

  • Vacations
  • “All hands” meetings
  • Off-site meetings (even if they are half days, consider the travel, etc.)
  • Training sessions (full day and/or off-site)
  • Sick days

Recording sick days can be really handy when a team member misses a few days of work and the ability for them to still complete their work request on the originally estimated completion date is infeasible. Additionally, as the weeks go by it becomes increasingly difficult to remember such loss of work days occurring in the past. This data can be critical to have captured and clearly reported on over time when the delivery date is fast approaching and requestors are starting to challenge the status of the work request progress or perceived lack of progress.

Special Assignments

Another body of work that deserves reporting recognition is the special assignment. From the typical situation:

Manager: Hey, can you look into what systems will be impacted when we start the FlimFlam upgrade project and let me know by next Friday before the quarterly project review meeting?

Team Member: Sure.

You asked that team member to do that work because it is important for your meeting. Now adding that request as a new single Gantt row of work accomplishes a number of goals:

  • Records the request so both you and the team member know it was made and when it is due.
  • Reflects that request along side the other work that team member is actively working on.
  • Communicates to other team members what each other are working on beyond just formal request and project work.
  • Communicates to outside parties all the work required by your team to perform the services they are charged with beyond just the formal request and project work.

In the act of recording the request you might (hypothetically) notice that the team member has a critical work deliverable due that same Friday. You have the opportunity to follow-up with that team member to remind them of their deliverable due dates, reset priorities or re-assign the request to another team member.

Again, you will need to develop your effective level of detail in reporting these non-external work requests. Your goal should be to strike a balance between overly detailed and thus time consuming to track compared to too little detail and thus requests get missed or lack external visibility.

On Going Assignments

You may want to consider adding on going assignments that don’t have a true end date to your report as well. An example might be investigating a new technology in order to consider its use in solving a formal work request in the future. I would suggest you put them at the very bottom of your report since they won’t change frequently. You may want to consider coming up with a unique color for these never ending requests. Since the time applied to these assignments varies, I wouldn’t try and update any work estimate durations around them unless you really want to enforce a team goal. A goal such as “spend 10% of your time investigating new technologies” should involve the reduction in about a half a day per week applied to all work estimates. This overall reduction formally allocates time for all to accomplish this goal from a work estimation perspective. Motivating your team members to meet their pressing external work deliverable dates plus invest time in learning new technologies at the same time is another matter.

At this point, you should have an even more accurate team resource plan reflected in your Gantt chart including all the major external and internal work items your team is engaged on. In the next article, I’ll suggest ways to keep the report from going stale and examples of the power of your resource plan possesses in improving how your are perceived as a manager in your organization.


Viewing all articles
Browse latest Browse all 10

Trending Articles